A mid-sized logistics company operating a fleet of 50 electric delivery vans in a major European city was facing growing pressure to reduce operational costs while maintaining high service levels. The company runs two depots where vans are charged overnight and during midday breaks. With increasing numbers of EVs and strict delivery deadlines, reliable charging infrastructure became critical.
The depot used a mix of outdated AC chargers and several DC units. The AC units were slow (3.3 kW), causing incomplete charging during the 4-hour window. The DC units were but expensive to install and operate, drawing high peak demand charges from the utility., the old AC chargers had frequent communication failures and poor cable management, leading to downtime and driver frustration. The fleet manager reported that 15% of vans left the depot with less than 80% state of charge, forcing route adjustments or late deliveries.
The company evaluated several vendors. They needed a solution that could deliver enough power within the limited time (7 kW minimum per van) without the high infrastructure cost of DC. The Soutya 7-14KW AC Charging Pile stood out because:
The purchasing decision was also influenced by the total cost of ownership: the Soutya units were priced 30% lower than comparable DC chargers, and installation was simpler because existing AC infrastructure could be reused with minor upgrades.
The project was executed in three phases over six weeks. Phase 1: site assessment and load analysis. The depot had a 300 kVA transformer; the team calculated that 20 units set to 7 kW each (140 kW total) would fit within the existing capacity after installing a smart load controller. Phase 2: installation of 20 Soutya 7-14KW AC Charging Piles on concrete plinths, each connected to a dedicated 40A breaker. Phase 3: integration with the fleet management software via OCPP 1.6. The biggest challenge was coordinating the old cable routing. The solution was to use pre-terminated cables with EN 50620 standard ratings to ensure flexibility and durability in the high-traffic depot.
After three months of operation, the fleet manager reported the following metrics:
The overall payback period for the investment was estimated at 14 months based on energy savings alone.
“The Soutya AC charging piles have been a important development for our depot operations. We no longer worry incomplete charging or peak demand penalties. The equipment works every day, and our drivers appreciate the reliable charging. It was a smart investment for our fleet.” — Fleet Operations Manager
Based on this project, other logistics companies should consider:
If the company were to repeat the project, they would install a dedicated transformer earlier to support future expansion beyond 20 units.


Jack
Soutya