Based in Austin, Texas, this solar engineering, procurement and construction (EPC) firm specializes in rooftop PV systems for distribution centers and logistics warehouses. The company installs 20 to 30 systems each year, ranging from 300 kW to 800 kW. Most of those rooftops are in jurisdictions that have adopted the 2020 revision of the National Electrical Code, meaning every system must have a listed rapid shutdown solution that reduces voltage within the array to ≤80 V within 30 seconds of initiation.
With a full-time field crew of 14 and an average project cycle of two months, the team needed a rapid shutdown approach that was both code-compliant and simple enough to keep installation moving across multiple job sites. The previous solution worked, but it came with hidden costs that did not show up in the bill of materials until late in the schedule.
The firm specified a module-level power optimizer system for rapid shutdown. Each box needed a proprietary communication link to a central gateway, and the gateway required a separate Ethernet cable and a 24 V DC control line back to the inverter area. On a 400 kW rooftop with more than 900 modules, that meant pulling extra low-voltage wiring along every module row and terminating it at three separate gateway locations.
Field technicians spent more time installing and troubleshooting these communication links than they did on the DC string wiring. Long wire runs occasionally dropped signals, causing the inverter's shutdown controller to report a fault. Even when the array was safe, intermittent communication failures triggered false alarms and failed inspections. One project required four site visits before the local AHJ accepted the shutdown timing test. The extra labor, rework, and inspection delays added $0.045 per watt to the company's installed cost.
While evaluating alternatives, the EPC team compared three options:
The Soutya device sends the shutdown command over the existing DC power cable, using a 24 V DC power line signal to communicate with module-level transmitters. There is no additional Ethernet run and no separate low-voltage sensor line. The enclosure mounts at every string combiner point and connects to a standard string inverter. A single controller can handle multiple strings, which reduces the number of control boxes needed per rooftop.
Another deciding factor was compatibility. The EPC was already standardized on one brand of string inverters, and the Soutya device works with inverters that do not have built-in rapid shutdown. That let the company keep its existing inverter inventory and transformer design, avoiding a costly rewiring of every project.
The first deployment happened on a 410 kW flat commercial roof in Dallas. The rollout spanned two phases over three weeks:
One obstacle appeared during the initial shutdown test. A weak ground connection caused the DC power line control signal to lose strength near the end of one long string. Soutya's application engineer advised installing a 10 m integrated signal filter at the end of that string. That resolved the issue in less than an hour. After the adjustment, the shutdown test measured 8 V at the module main connector within 22 seconds, comfortably under the 80 V limit.
The company tracked 18 completed rooftop systems after the first year of using the Soutya rapid shutdown device. Measured outcomes versus the previous approach:
Those gains allowed the EPC to absorb a later material price increase without changing its bid price, and the shortened construction schedule improved on-time delivery for warehouse tenants who needed their roofs operating .
"Module-level rapid shutdown used to be our biggest dirty work area," said the firm's VP of Operations. "The Soutya 24 V DC power line control device took one layer of complexity out of the whole system. We don't pull extra data wire anymore, and we haven't had a single shutdown communication failure since we switched."
Three lessons from this project stand out for other installers:
If the team could restart the project, they would put the signal strength filter on the design drawing from the beginning for any string longer than 300 m. Still, the minor adjustment was the only issue encountered across all 18 installations.